PROCEDURE
PROCEDURE |
Important | ||||||||||||||||||||
• |
During operation, be sure to
wear safety goggles and protective gloves.
|
|||||||||||||||||||
• |
Before charging the refrigerant, evacuate the system
to remove small amounts of moisture remaining in the system.
The moisture in the system can be completely evacuated only under the minimum vacuum level. The minimum vacuum level affects the temperature in the system. |
|||||||||||||||||||
• |
The list below shows the vacuum values necessary to
boil water in various temperature. In addition, the vacuum levels
indicated on the gauge are approx. 3.3 kPa (25 mmHg, 0.98 inHg) lower
than those measured at 304.8 m (1,000 ft) above sea level.
|
|||||||||||||||||||
Close the valves on low-/high-pressure sides of the manifold gauge.
(A)
|
Low-pressure
gauge (Compound pressure gauge)
|
(B)
|
High-pressure
gauge
|
(C)
|
Close
|
Install the low-/high-pressure hoses to the corresponding service ports on the vehicle respectively.
Connect the center hose of the manifold gauge set with the vacuum pump.
Carefully open the valves on the low-/high-pressure sides to activate the vacuum pump.
(A)
|
Low-pressure
gauge (Compound pressure gauge)
|
(B)
|
High-pressure
gauge
|
(C)
|
Slowly
open
|
(D)
|
Vacuum
pump turn on
|
After the low-pressure gauge reaches 100.0 kPa (750 mmHg, 29.5 inHg) or higher, evacuate the system for approx. 15 minutes (Continue evacuation).
After 15 minutes of evacuation, if the reading shows 100.0 kPa (750 mmHg, 29.5 inHg) or higher, close the valves on the both sides to stop the vacuum pump.
(A)
|
Low-pressure
gauge (Compound pressure gauge)
|
(B)
|
High-pressure
gauge
|
(C)
|
Close
|
(D)
|
Vacuum
pump turn off
|
Note the low-pressure gauge reading.
Leave it at least 5 minutes, and then check the low-pressure gauge reading for any changes.
When a gauge indicator shows near to zero point, this is a sign of leakage. Check pipe connector points, repair them, make sure there is no leakage by air bleeding.
Following the can tap operation manual instructions, install it to the refrigerant can.
(A)
|
Tap valve
|
(B)
|
Center
manifold hose
|
Disconnect the center manifold hose from the vacuum pump, and connect the hose to the tap valve.
When a 13.6 kg (30 lb) refrigerant container is used, measure the refrigerant amount in use using a weighting scale.
(A)
|
Refrigerant
container (HFC-134a)
|
(B)
|
Weight
scale
|
Confirm that all the 3 hoses are tightly connected to the manifold gauge set.
(A)
|
Low-pressure
gauge (Compound pressure gauge)
|
(B)
|
High-pressure
gauge
|
(C)
|
Close
|
Open the valve on the HFC-134a source.
Loosen the center hose connection on the manifold gauge set (if applicable, press a purge valve on the manifold gauge set) only for a couple of seconds to allow the air in the center hose to escape by the refrigerant.
Carefully open the high-pressure valve with the engine stopping.
Important | ||
Do not open the low-pressure valve. |
||
(A)
|
Low-pressure
gauge (Compound pressure gauge)
|
(B)
|
High-pressure
gauge
|
(C)
|
Close
|
(D)
|
Ignition
switch OFF
|
(E)
|
Slowly
open
|
Important | ||
Never run the engine during charging from the high-pressure side. |
||
Close the high-pressure valve when the low-pressure gauge reaches 98 kPa (1 kg/cm 2 , 14 psi). Using a leak tester, check the system for leaks.
If any leakage is found after the refrigerant recovery is completed, repair the applicable area.
After confirming that there are no leaks with the leak test, charge the required amount of refrigerant.
Important | ||
Never run the engine during charging from the high-pressure side. |
||
Close the high-pressure valve when;
• |
the readings
of low-/high-pressure gauges become almost equal, after
the charging speed is reduced,
|
• |
the HFC-134a source becomes empty, or the system is
filled with the gas.
|
If the HFC-134a source is empty, close the high-pressure valve, close the valve on the can tap, and replace the HFC-134a source with a new one to restart the operation.
(A)
|
Low-pressure
gauge (Compound pressure gauge)
|
(B)
|
High-pressure
gauge
|
(C)
|
Close
|
Confirm that both the low-/high-pressure valves can be closed. Start the engine with the A/C switch OFF.
Quickly repeat ON-OFF cycles a few times to prevent initial compressor damage.
Set up the vehicle to the following status:
• |
A/C
switch ON
|
• |
Engine running at 1,500 rpm
|
• |
Blower speed setting to “HI”
|
• |
Temperature setting to “MAX COOL”
|
• |
Air inlet setting to “RECIRC”
|
• |
Windows open
|
While reading the low-pressure gauge, carefully open the low-pressure valve with the refrigerant source connected and the service hose purged.
Important | ||
Never open the high-pressure valve with the engine running. Doing so may result in a reflow of high-pressure gas and refrigerant can’s explosion. |
||
Adjust the refrigerant flow to maintain the pressure on the low-pressure side at 276 kPa (2.81 kg/cm 2 , 40 psi) max.
After the system is fully charged, close the low-pressure valve.
Close the valve on the refrigerant source.
Refrigerant amount
|
||
Refrigerant
|
Minimum
|
Maximum
|
HFC-134a
|
450
g (0.99 lb)
|
550
g (1.21 lb)
|
Disconnect the hose from the service port, and install the service port cap.